07/23/2026

Multiple fiber optic providers are completing infrastructure work in different areas of the Township. Residents may see several companies installing fiber optic infrastructure in neighborhoods throughout the Township.

Commerce Township has communicated updated notification requirements to all fiber installation companies working within the Township. Companies must provide advance notice of upcoming work so that residents can stay informed.

As construction schedules and project information are provided to the Township, updates- including planned work locations, resident notices to below, and available contact information for each installation company- will be posted on this page. Please note that the Township can only share information as we receive it from the installation companies. We appreciate your patience as these projects continue throughout the community. Contact information for each company is also below.

Questions or Inquiries for WOW!:

If you have any issues during the construction process or after restoration, please contact their customer advocates and escalation team by calling 248-773-5022 or to: mich.construction@wowinc.com.

Two weeks before construction, WOW will hang a door hanger on your door to let you know they’re in your area. Here is a note from WOW regarding construction in progress: "Regarding utility markings, workers from your local utility company or contract partner will place markings in the easement to identify the location of underground utilities. Please leave these in place and we will remove them when construction has been completed. Regarding construction, when your area is ready, crews will start laying fiber underground or attaching lines to existing utility poles. Our team members may need to access the utility easement or right of way. We’ll take special care of your lawn and perform necessary restorations due to construction. You can help us by marking any sprinkler systems, invisible dog fences, or private lighting wires.”

 7/30/26 WOW Updates:
Crew one will complete Jason Dr (CM05-E) and move onto Birkdale Dr (CM05-E)
Crew two will Complete the east side of Applebrook and then move west (CM05-D)
Crew three will complete Cooley Lake and move into the subdivision off of Venice Dr (CM04-C)
2 Crews will complete Glengary Rd East and West of Benstein Rd on OK0HB and OK0HD

Questions or Inquiries for T-MOBILE:

If you have any issues during the construction process or after restoration, please contact their customer advocates at this phone number or website: 877-386-3876 | Metront.com/construction

Questions or Inquiries for Bell Wire Communication Construction LLC.:

Website: https://www.bellwirecommunicationconstruction.com/

7/30/26 Bell Wire Update:
We are currently working on Permit PUR25-176 in the areas of Ecommerce & Wise, Lancaster and Bogie Lake.The underground boring is almost complete. Placing will start shortly after the boring is complete.This job should be complete within a couple of weeks.